Client
Digital Realty Richardson
Services
  • Design Management
  • Design Review
  • OFCI Equipment Procurement
  • Construction Management
  • City Coordination
  • IT Integration Management
  • Commissioning Management
  • Project Closeout

850 E. Collins, Suites 150 & 160 is a $30 million project completed via a very fast-track schedule. Scope of work was inclusive of an interior finish-out of the office area, conference rooms, restrooms and other public support spaces. The data center finish-out included (2) 10,000 SF of raised access flooring and a critical power system rated at 1125 KVA; 1.125 MW each. The data centers with powered with modular skid frame-mounted electrical switchgear and UPS equipment which was fabricated offsite from the project. This method allowed for simultaneous construction of the data center suites and fabrication of the critical electrical equipment.

The design – construction – commissioning process for the two (2) data centers was completed in 30 weeks; less than 7 months.